Construction Progress Phase VII
|
 |
 |
The hull plug receives the first coats of laminate to form the mold |
|
 |
 |
The deck mold arrives at Morris Yachts in Maine |
|
 |
 |
SP High Modulus provides the custom cut laminate and core materials in their SmartPac. These items are cut, utilizing the computer 3D modeling. |
Each piece of material is plotted on a detailed plan of the deck mold |
 |
 |
The first layer of laminate material is placed in the mold according to the layout plan |
|
 |
 |
The laminate is trimmed around the forward hatch. Note the two port openings. |
The core material is now placed on its corresponding laminate material |
 |
|
After the core material is put in place, another layer of laminate material will be placed on top, forming a sandwich of material ready to have the resin infused to create the deck. |
|
|
|